Construction Update

Brief History

With growing number of Muslims in Marshfield and vicinity, in early 2003 we felt that a small masjid (mosque) was very much needed in the area. Thanks to almighty God (Alhumdulillah), we were able to buy 1.5 acre land near the St. Joseph Hospital and the Marshfield Clinic. All the planning and designing was done with the consideration of current community needs, future expansion, Dawa work and open House facility for non-Muslims and for media relations. The total project cost including the land has come to $400,000. Alhumdulillah, we were able to collect (within community) $230,000 with the fundraising over the last ‘three’ years. With consensus in community, we recently signed the contract with Henrick’s Builders (who enjoys an excellent reputation in the area) and started the building in the first week of August 2006.

(We would appreciate your generous donation to meet the construction/maintenance budget and daily expenses.
Please visit Donation page for more information. JazakAllah)

Project Update

Date Description Pictures
April 30, 2012 Rain gutters were installed.
October 31, 2011 Safety grills are installed in the backyard.
May 31, 2010 Parking lot with black top completed.
July 31, 2008 Multipurpose room/Library and basement including kitchen and Imam Office completed.
February 22, 2007 First prayer of the mosque is established (as Maghrib prayer). Inside prayer hall, restrooms, ladies prayer hall and the Hallway are finished with carpeting. Occupancy permit is issued by the state. Click to View
February 09, 2007 All Painting is completed (in the finished area). All Inside windows, doors and railing work is finished. Flooring in bathrooms are done. Waiting for bathroom partitions, carpeting and outside railing and door work. Click to View
January 10, 2007 Priming is completed in the finished area. Ready for painting, electrical and trim work. Click to View
December 12, 2006 Other then basement and lounge, all dry wall work is completed. Click to View
December 06, 2006 Gas meter, parking lights and fiber glass insulation completed. Click to View
November 17, 2006 Sidewalks are completed and cement is settling down. Click to View
November 12, 2006 Alhumdulillah, the mosque is near completion from the exterior. All the windows are installed. Roof is completed with minaret towards northwest side of the building. All retaining wall work by the basement entrance is completed. Interior needs to be dry walled and painted. Click to View
October 06, 2006 All flat rubber roofing is completed. Construction for base of future possible dome is started. Click to View
October 03, 2006 First floor is near completion, Second floor and roofing for entire building has begun. Click to View
September 07, 2006 Roof work for basement near completion. Now one can walk on Main floor. Click to View
September 01, 2006 Main floor construction started. Floor for prayer hall, lounge and restrooms have started. Click to View
August 19, 2006 All cement work completed. Sand is poured back, ready for the upper floors. Click to View
August 14, 2006 Cement and woodwork for the basement has started, foundation work near completion. Click to View
August 06, 2006 Qibla direction was determined and excavation/concrete work has started. Click to View